In order to use the WACC to evaluate a future project's flows, which of the following must hold?

In order to use the WACC to evaluate a future project's flows, which of the following must hold?



A) The project will be financed with the same proportion of debt and equity as the firm.
B) The systematic risk of the project is the same as the overall systematic risk of the firm.
C) The project must be viable.
D) a and b above.



Answer: D