If a firm were interested in knowing the effect of a single input change on the net present value of a project, then the firm would most likely want to perform

If a firm were interested in knowing the effect of a single input change on the net present value of a project, then the firm would most likely want to perform



A) a Monte Carlo simulation.
B) scenario analysis.
C) sensitivity analysis.
D) none of the above.


Answer: C